TL;DR · 30-second read
The Short Version
Hyperscale Data, a Las Vegas company that is losing money today, told investors it expects $300 million to $350 million in sales next year. It also expects $60 million to $80 million in earnings before interest, taxes and wear-and-tear costs.
Much of that rests on one project. A former Bitcoin-mining site in Michigan is being rebuilt to run artificial intelligence computers for a single customer, on a 10-year deal that can stretch to 20.
The site needs 20 megawatts of power, roughly what a small town uses, switched on by the end of March. If the build slips, so does the forecast.
On November 23, 2026, Hyperscale Data, Inc. (NYSE American: GPUS) reaffirmed its preliminary 2027 guidance of $300 million to $350 million in revenue and $60 million to $80 million in adjusted EBITDA. The guidance includes the results of its Ault Capital Group (ACG) subsidiary regardless of when ACG’s planned 2027 divestiture occurs. The company filed the guidance release, an investor-day presentation and a leadership-change announcement with an 8-K the same day, ahead of an earnings call and Investor Day.
The centerpiece is the company’s Michigan AI data center in Dowagiac. There it is developing approximately 20 MW of critical AI compute capacity for a California-based neocloud customer. The first 10 MW is targeted for December 2026 and the second 10 MW for the end of March 2027.
Executive Summary
Hyperscale Data is guiding to a sharp step-up in 2027. Revenue is projected at $300 million to $350 million and adjusted EBITDA at $60 million to $80 million, compared with nine-month 2026 revenue of $123.8 million and a nine-month net loss of $62.1 million. The company has a signed customer for its Michigan campus: a 10-year master services agreement with two five-year extension options. It values that agreement at approximately $1.2 billion over 20 years if both extensions are exercised.
Demand, in other words, is contracted. What remains open is delivery. The company states that its December and March targets are subject to financing availability, construction progress, equipment procurement, commissioning and customer deployment requirements. Its own leadership succession is also tied to the same milestone: founder Milton “Todd” Ault III plans to step down as Co-Executive Chairman once the campus is fully energized.
For investors and for the wider AI infrastructure market, the announcement is a clear example of a pattern. Once a tenant is signed, the forecast depends on energizing megawatts on schedule. A slip in either 10 MW tranche would land directly inside the year the guidance covers.
The Tenant Is Signed. The Megawatts Are the Risk.
Many early-stage AI data center stories turn on whether a developer can find a customer. Hyperscale Data has already cleared that hurdle. Its third-quarter results, released November 19, describe a master services agreement with a California-based neocloud, meaning a cloud provider focused on renting out AI computing. The agreement covers approximately 20 MW of critical AI compute capacity at the company’s campus in Dowagiac, Michigan. Critical capacity is the power available to the computing equipment itself, separate from the power used for cooling and other overhead. The agreement runs 10 years, with two five-year extensions at the customer’s option.
That shifts the question from demand to delivery. The company is targeting December 2026 for the first 10 MW and the end of March 2027 for the second. It states that the schedule “remains subject to financing availability, construction progress, equipment procurement, commissioning and customer deployment requirements.” The guidance release lists a similar set of dependencies: power availability, financing, approvals, customer elections and delivery. 2027 is the first year in which the full Michigan capacity could bill, so a slip of even one quarter would fall inside the guided period.
The investor-day presentation filed with the November 23 8-K frames the Michigan discussion around “December target and funding.” The company’s leadership change is tied to the same date, since Ault plans to step down as Co-Executive Chairman after the campus is fully energized. That puts the energization milestone at the center of the company’s own narrative.
What a $1.2 Billion Contract Means for One Year
The company values the initial 20 MW at approximately $1.2 billion over a 20-year term. That figure assumes the customer exercises both extensions and the company meets its obligations. Spread evenly, it works out to roughly $60 million a year. This is only a crude average. The company has not disclosed the pricing schedule, any escalators, or whether the figure includes pass-through electricity costs. And 2027 will not be a full year at 20 MW, because the second tranche is not targeted until the end of March.
Set that against the rest of the business. Nine-month 2026 revenue was $123.8 million, or about $165 million on a simple annualized basis. That base included $12.0 million of Bitcoin mining revenue from a site that stopped mining on September 1. Even crediting Michigan with a full $60 million, the remaining operations would need to generate roughly $240 million to $290 million to reach the guided range. Part of this year’s growth came from lending and trading revenue, which the company says was driven primarily by unrealized gains on equity investments, a line that can swing with markets.
On the disclosed arithmetic, then, the Michigan build looks necessary to the guidance but not sufficient on its own. The investor-day materials point to growth in the ACG portfolio as the other leg. Investors will want to see how management splits the range between the two.
From Operating Losses to $60M–$80M Adjusted EBITDA
The profit guidance is the steeper climb. In the third quarter, operating expenses of $29.9 million were nearly three times gross profit of $10.5 million. The quarter’s $13.0 million net loss was cushioned by about $9.2 million of gains on crypto assets and $4.0 million from changes in the fair value of embedded derivative liabilities. Nine-month operating expenses roughly doubled to $98.1 million, and the nine-month net loss widened to $62.1 million from $35.6 million.
Adjusted EBITDA adds back interest, taxes, depreciation and amortization, plus other items management excludes, so by design it will look better than net income. Even so, reaching $60 million to $80 million requires a large new source of operating profit. Long-term colocation revenue, from renting a tenant space, power and cooling under a multi-year contract, is the most plausible candidate in the disclosed business. That is why the Michigan timeline weighs so heavily on the EBITDA range. The company says it cannot reconcile projected adjusted EBITDA to GAAP net income without unreasonable effort, because interest expense and fair-value changes cannot be reliably estimated. Interest expense is closely linked to how the build is financed.
The Capital Structure Is Moving at the Same Time
The build is proceeding alongside several balance-sheet changes. In an 8-K filed November 19, the company disclosed an exchange offer for its Class A common stock. Tendering stockholders receive, for each block of 100 shares, one share of a new 12.00% Series I Cumulative Redeemable Perpetual Preferred Stock plus $2.00 in cash. The company describes it as a $50 million offer for up to 192,308,000 shares. Cumulative preferred dividends rank ahead of common stockholders, and they already weigh on results. Third-quarter net loss attributable to common stockholders was $18.0 million, against a net loss of $13.0 million.
Separately, the planned 2027 divestiture of ACG would leave Hyperscale Data as a data center operator that also holds digital assets and Omnipresent Robotics. The 2027 guidance explicitly includes ACG’s results regardless of when that separation occurs. For anyone valuing the post-divestiture company, the Michigan contribution is the number that matters most. That makes the December and March milestones even more central than the headline range suggests.
Background
Hyperscale Data, Inc., based in Las Vegas and listed on NYSE American under the ticker GPUS, describes itself as an AI data center company. Its subsidiary Sentinum owns and operates data center capacity offering colocation and hosting. Its holding company, Ault Capital Group, owns businesses across financial services, digital assets, crane services, defense, hospitality and other sectors, including Ault Lending, Circle 8 Crane Services and Gresham Worldwide. The company plans to divest ACG in 2027 and become a pure-play AI data center operator, with the Michigan campus as its flagship. It would retain its digital assets and Omnipresent Robotics.
The Michigan campus previously ran Bitcoin mining, which stopped on September 1, 2026, ahead of the move to AI hosting. Converting crypto-mining sites to AI use has become a common route into the market, because those sites already have substantial power connections and land. Whether such conversions succeed depends on how quickly operators can finance, equip and energize capacity to the standards AI tenants require. Source: Hyperscale Data Reaffirms 2027 Guidance of $300 Million to $350 Million in Revenue as Well as $60 Million to $80 Million in Adjusted EBITDA and Invites Stockholders to Today’s Conference Call, the company’s November 23, 2026 announcement reaffirming 2027 guidance ahead of its Investor Day. Primary sources: Hyperscale Data Form 8-K filed November 23, 2026; Exhibit to November 23, 2026 8-K: November 2026 Investor Day presentation; Exhibit to November 23, 2026 8-K: Hyperscale Data Names William B. Horne Co-Executive Chairman Alongside Milton “Todd” Ault III; Hyperscale Data Form 8-K filed November 19, 2026; Exhibit to November 19, 2026 8-K: Hyperscale Data Reports Third Quarter 2026 Revenue of $44.8 Million, 84% Increase over Prior Year Period.Sources